RERA in Gurugram: the CA certificates for each quarter and the annual audit due by 30 September

How the 70% separate account works, what the architect, engineer and chartered accountant certify every quarter, what goes into the annual filing, and the late fees HARERA Gurugram charges.

Lukesh Sethi & Associates28 November 20266 min read
RERA in Gurugram: the CA certificates for each quarter and the annual audit due by 30 September

Every promoter of a registered real estate project has to keep buyers' money in a separate bank account and take it out only as construction progresses. Each withdrawal and the annual accounts for the project have to be certified by a chartered accountant in practice. In Gurugram, the Haryana Real Estate Regulatory Authority (HARERA) has prescribed the formats and the due dates.

1. The 70% rule

Section 4(2)(l)(D) of the Real Estate (Regulation and Development) Act, 2016 requires that 70% of the amounts realised from allottees for a project be deposited in a separate account with a scheduled bank. The money in that account can be used only for the cost of construction and the land cost of that project. Three conditions sit on top of it:

  • Withdrawals must be in proportion to the percentage of completion of the project.
  • Each withdrawal must be certified by an engineer, an architect and a chartered accountant in practice.
  • The promoter must get the accounts audited by a chartered accountant in practice within six months after the end of every financial year, with a statement of accounts certified by that chartered accountant. The audit must verify that money collected for a project was used for that project and that withdrawals were in proportion to completion.

The 70% applies to money actually collected from buyers, not to the sale value of the units.

2. How HARERA Gurugram applies it

HARERA Gurugram issued directions on section 4(2)(l)(D) on 2 March 2020 and the HARERA Gurugram [Compliance of Section 4(2)(l)(D)] Regulations, 2020 on 6 July 2020. Under them, collections from buyers go first into a master account, and are split 70% to the separate RERA account and 30% to a free account. Neither the master account nor the separate account may carry charges or encumbrances.

3. Quarterly certificates

CertificateGiven byWhat it covers
Annexure AArchitectProgress of construction
Annexure BEngineerPercentage of completion and estimated cost
Annexure CChartered accountantWithdrawal of money from the separate RERA account at the end of the quarter

These are filed with the quarterly progress report. HARERA Gurugram's 2018 regulations on quarterly progress reports require the report to reach the Authority before the 15th of the month after the quarter ends, so the report for the quarter ending 31 December 2026 is due before 15 January 2027.

4. The annual filing by 30 September

For each financial year, the promoter must file by 30 September:

  • The Annual Report on Statement of Accounts, certified by the chartered accountant, answering the compliance questions in the prescribed form.
  • Formats AFS-I to AFS-VIII: the master account (AFS-I), the separate RERA account (AFS-II), expenditure out of the separate account (AFS-III), project viability (AFS-IV), the project balance sheet, income and expenditure and cash flow (AFS-V), financial and physical progress at the year end (AFS-VI and AFS-VII), and the promoter's undertaking that buyers' money was used only for the project (AFS-VIII).
  • Copies of every chartered accountant's certificate issued for withdrawals during the year, and Annexures A, B and C for all four quarters.

The filing for FY 2025-26 was due on 30 September 2026. Promoters who have not filed it are already paying a late fee.

5. What the auditor reports on

  • Whether collections were split 70:30 between the separate account and the free account.
  • Whether withdrawals were only for construction, land cost and statutory dues, and within the limit certified.
  • Excess withdrawals, loans or borrowings against the account, and transfers to related parties.
  • Receipts of more than 10% of the cost of a unit without a registered agreement for sale.
  • Differences between the architect's, engineer's and chartered accountant's quarterly certificates.

6. Consequences of non-compliance

Delay in the annual filingLate fee
Up to one month₹10,000 per day
More than one month, less than three months₹25,000 per day

The Authority may also start proceedings under sections 60 and 63 of the Act, ask for more information, or order a forensic audit at the promoter's cost where the information filed appears incorrect or is not filed. Section 60 provides for a penalty of up to 5% of the estimated cost of the project for contravening section 4.

7. A checklist for promoters

  1. One master account and one separate RERA account for each project or phase, opened with a scheduled bank.
  2. A monthly reconciliation of collections with the 70:30 transfers.
  3. No withdrawal from the separate account without the three certificates for that withdrawal.
  4. Project-wise books, so that cost incurred can be tied to the engineer's percentage of completion.
  5. A calendar for the quarterly progress report (before the 15th after each quarter) and the annual filing (30 September).

Projects outside Gurugram district are regulated by HARERA Panchkula, which has its own directions and formats; the requirements of the Act itself are the same.

General information on the law as at 28 November 2026. It is not professional advice; please read the official notification on the Government website and take advice on your facts.

Questions on how this applies to you?

Ask about this updateAll articles

Newsletter

Tax and compliance updates by email

A short note when GST, income-tax, TDS, company-law or labour-law rules change, with the dates that matter. Sent only to those who ask for it. Unsubscribe any time by replying "Unsubscribe".