Solar and renewable energy: GST at 5% on devices and the 70:30 rule for EPC contracts

Renewable energy devices moved from 12% to 5% on 22 September 2025. Turnkey solar contracts are taxed on a deemed 70:30 split, and generators selling power cannot use most of their credit.

Lukesh Sethi & Associates28 November 20264 min read
Solar and renewable energy: GST at 5% on devices and the 70:30 rule for EPC contracts

GST on renewable energy equipment was cut on 22 September 2025. The change affects equipment suppliers, EPC contractors and developers differently.

1. Devices at 5%

Solar power generating systems, solar power-based devices, photovoltaic cells and modules, wind-operated electricity generators, waste-to-energy plants and devices, biogas plants and tidal energy devices, and parts for their manufacture, are taxed at 5% (earlier 12%).

2. EPC and turnkey contracts

Where a solar or wind plant is supplied with design, installation or construction services under one contract, the rate notification deems 70% of the gross consideration to be the value of the goods, taxed at 5%, and 30% to be the value of services, taxed at 18%. The effective rate is about 8.9%, against about 13.8% before the change. The split applies whatever the contract itself says about the value of goods and services.

3. Contracts that straddle the date

The rate that applies depends on the time of supply: the earlier of the invoice and the receipt of payment, with special rules where the rate changes in between. Contracts bid before 22 September 2025 but billed afterwards should be repriced; the Central Electricity Regulatory Commission has treated the reduction as a change in law for projects bid before that date.

4. Developers selling electricity

Supply of electricity is exempt from GST. A developer whose only output is electricity cannot use the GST paid on the plant, so the tax becomes part of the project cost. Developers that also supply taxable services, such as operation and maintenance to others, should apportion credit carefully.

5. Income tax

The cost of the plant, including the GST that cannot be credited, is depreciated as plant and machinery. Rooftop systems installed by a business for its own use are capital expenditure, not an expense.

6. A checklist

  1. HSN codes and rates updated for equipment sold after 22 September 2025.
  2. Turnkey contracts invoiced on the 70:30 basis.
  3. Contracts spanning the change reviewed for time of supply and price adjustment.
  4. Credit position of generating companies reviewed, with non-creditable GST capitalised.

General information on the law as at 28 November 2026. It is not professional advice; please read the official notification on the Government website and take advice on your facts.

Questions on how this applies to you?

Ask about this updateAll articles

Newsletter

Tax and compliance updates by email

A short note when GST, income-tax, TDS, company-law or labour-law rules change, with the dates that matter. Sent only to those who ask for it. Unsubscribe any time by replying "Unsubscribe".